The engineering behind a constrained connection — designed, built and supported by the manufacturer of a Fully Type Tested scheme.

Built on the ENICO G100 Controller — fully type-tested to EREC G100 Issue 2 Amendment 2, ENA Type Test Register ref. ENICT/19509/V1

When export limitation applies

The DNO's connection offer caps your export below what your generation could produce — a constrained network, a shared transformer, a cautious planner. Without an export limitation scheme, your choices are to shrink the system or pay for reinforcement. With one, you size the system to the site and hold export inside the agreed figure, within the response times G100 sets.

That is what EREC G100 — currently Issue 2 Amendment 2, G100/2 for short — governs: how export is measured, how fast the scheme reacts, what happens if measurement or communications are lost. For a scheme listed on the ENA Type Test Register, commissioning day is a set of safety checks, not a full demonstration.

The whole scheme, designed and built

A G100 scheme is measurement at the right point of supply, control that actually reaches your inverters and generators, fail-safe behaviour that defaults the site to a safe state, and the documentation your DNO submission needs.

ENICO designs the whole scheme and builds it into real switchgear — a standalone panel, or integrated into the PV distribution board or main switchboard where it belongs. One assembly, one set of documentation, one point of responsibility.

Single site or distributed

Compact sites need one measurement point and one controller. Large sites — multiple inverter groups, long cable runs, solar farms — need a distributed architecture that manages many control points as one scheme, over fail-safe communication links. We build both; the distributed case has its own page.

The DNO journey, supported

From reading the connection offer to the day the settings are sealed: we confirm what the offer actually requires, engineer the scheme to match, supply the Appendix C paperwork carrying our register reference, and support any on-site testing the DNO chooses to carry out.

Where G100 meets the rest of the site

An export limit changes how the whole site should behave: it strengthens the case for using generation on site rather than spilling it, and it has to coexist with peak-shaving schemes and battery control without the two fighting. The pages below cover both. Where the constraint is on the import side — charging hubs, grid-charged storage, heat pumps — the import limitation page covers it.

Monitoring & verification

An export limit you can't see is an export limit you can't trust. We pair G100 schemes with the Plantstream monitoring platform — for solar, capable of IEC 61724-1 Class A performance monitoring — so export, generation and curtailment are visible and verifiable for the life of the installation.

Constrained connection on the table?

Send the connection offer and your generation schedule — an engineer will tell you straight what the scheme needs, what it doesn't, and what it should cost to find out.