// ENA EREC G100 · Issue 2 Amendment 2 (G100/2)
G100 export and import limitation panels — fully type-tested.
ENICO G100 Controller is fully type-tested to EREC G100 Issue 2 Amendment 2 for both export and import limitation, and listed on the ENA Type Test Register — supplied as a standalone panel or built into your switchgear, with the compliance pack your DNO submission needs.
- Fully type-tested to EREC G100 Issue 2 Amd 2 — export and import
- ENA Type Test Register · ref. ENICT/19509/V1
- Standalone panel or fully integrated
What is export and import limitation?
When you apply to connect solar, storage or other generation, the distribution network operator (DNO) often offers an export capacity lower than the generation you would like to install. An export limitation scheme lets you size the system to the site instead. It measures what the site is exporting at the point of supply and holds export within the agreed limit — by simple disconnection on smaller schemes, or by trimming output continuously so the site keeps generating.
Import limitation works the same way in the other direction. Your connection agreement also caps what the site may draw. New loads — DC rapid chargers, a battery filling from the grid, heat pumps replacing gas plant — can push a site past that figure if they all run at full power together. An import scheme measures net import at the point of supply and holds controllable load back as the site approaches the limit, so the site can carry more installed load than it could run flat out together, within the limit agreed with the DNO.
EREC G100 covers both. Its full title is Technical Requirements for Customers' Export and Import Limitation Schemes, and the same rules apply to each: measurement at the connection point, brief time-limited excursions (short overshoots while the scheme acts), fail-safe behaviour and tamper-protected settings. The scheme holds the DNO's limit and fails safe in either direction, and your system is sized to what the site needs.
Constraint on the import side? Charging hubs, grid-charged batteries and electrified heating have their own page: G100 import limitation for EV charging hubs and BESS
A smooth route to connection
The ENICO G100 Controller is Fully Type Tested to G100 for export and import and listed on the ENA Type Test Register. That ENA-approved listing means your DNO recognises what it is connecting before the panel leaves our works. Commissioning day is a set of safety checks, not a full demonstration — less to test, less to book, less to witness. The same controller goes into every panel, so your next site follows the same route as your last.
On sites that need it, the ENICO controller trims output to hold your agreed limit continuously. You keep generating through the hours when the limit bites.
View our register entry
ENA Type Test Register: our entry, as published
- Reference
- ENICT/19509/V1
- Manufacturer
- ENICO LTD
- Model (as registered)
- ENCO G100/2 Controller
- Type
- Stand-alone G100 Device
- Phases
- 3
- Compliance status
- Compliant
- G100 (GB) Fully Type Tested
- Yes
- Published
- 26 March 2026 (last modified 9 April 2026)
- Last checked by ENICO
- 15 October 2026
Model name shown exactly as it appears on the register; ENICO is asking the ENA to correct the spelling.
Source: our entry on ENA Connect Direct (opens in a new tab)
How the scheme works
- Step 1
Measure at the point of supply
The scheme meters net flow at the supply intake, the point your DNO's limit applies to. Export on an export scheme, import on an import scheme. Not a single circuit, not a single charger.
- Step 2
Detect the excursion
As export approaches the Maximum Export Limit (MEL), or import the Maximum Import Limit (MIL), the controller reacts within the response times G100 sets. G100 allows brief, time-limited excursions — short overshoots while the scheme acts — and sets how quickly flow must return within the limit.
- Step 3
Act — trip or trim
Export: disconnect generation, or ramp it down so the site keeps generating. Import: hold controllable load back (charger power, battery charging) so the rest of the site keeps running. G100/2 allows simple and dynamic schemes; we engineer the one that suits the site.
- Step 4
Fail safe, always
Loss of measurement, comms or power drives the scheme to its safe state — generation to a safe state on an export scheme, load shed or reduced on an import scheme. After repeated or prolonged excursions the scheme holds its safe state until it is reset, as EREC G100 requires, and its logs show what led to it.
A third option — dump load control. Where generation cannot be controlled dynamically — some wind turbines, CHP, hydro and older inverters — the scheme can divert surplus into a controllable load instead: heating, hot water or a thermal store. The energy stays on site and does useful work. If the scheme goes to its safe state, it still acts on the generation. Dump load control is an ENICO option, engineered to the site.
Why sites need G100
Cover more of your own load
Many sites have a high load and a low export limit. Export is not the goal; reducing spend is. A G100 scheme lets you size generation to the load even where the export limit is small or zero, holding export within it when demand drops. Every unit used on site is one less to buy.
Solar sized for the whole year
An array sized to fit the export limit on a summer peak is small for the rest of the year. Size it for the year instead, and it generates more in autumn, winter and spring. The limit mainly bites on bright summer days, and the scheme trims those peaks rather than forcing a smaller array.
Wind sized for annual energy
Payback comes from the energy a turbine captures over the year, not its peak power. Size the turbine for the most energy, and full output arrives only in the windiest hours. Export limitation handles those rare peaks, so the turbine is sized for payback, not for the limit.
EV charging, batteries and heat pumps
Chargers, batteries charging from the grid and heat pumps can take a site past its import limit if they all run at full power together. An import scheme holds controllable load back as the site nears the limit, so new load can go in within the connection you already have.
How the route works
The ENICO G100 Controller is Fully ENA Type Tested: its control functions were validated in that type test, so ENICO's part of your DNO submission is complete the day the panel ships. It arrives pre-configured, with the commissioning paperwork prepared.
On site, testing reduces to the fail-safe checks: that the controller goes to its safe state if power or communications are interrupted. Where your DNO chooses to witness commissioning, the visit is booked into its diary, may be chargeable, and the lead time can hold up energisation. EREC G100 sets out what that visit has to cover. We support the visit.
After acceptance the settings are sealed, excursion counters and timers are held in memory, and you can interrogate the controller, so any excursion or trip can be diagnosed easily from its logs.
G100 in numbers
15 s
An overshoot of your limit shorter than this is not counted as an excursion; longer ones are counted and timed.
EREC G100 cl. 4.3.2, 4.5.1.3
1 min / 3 min
Default maximum time to bring flow back within your limit; 3 min for slow-acting plant on industrial and commercial sites unless your DNO identifies a voltage problem.
EREC G100 cl. 4.3.2
10 s
ENICO's declared time for the G100 Controller to reach its safe state on loss of communication; the standard allows up to 15 s.
EREC G100 cl. 4.5.1.2
4 h
On a non-domestic site, the minimum time before a trip after repeated or prolonged excursions can be reset; after a loss of communication, it can be reset as soon as the link is restored.
EREC G100 cl. 4.5.2.1, 4.5.2.2
// On-panel interface
See what the controller is doing
Every ENICO G100 Controller carries its own interface — on the panel display and in the browser for anyone on the site network. One screen answers the questions that matter: how close is export to the agreed limit, what has the scheme done about it, and when.
- Live connection-point current against the MEL, phase by phase
- Trend and event views that make commissioning and witness testing straightforward
- A plain status banner — green means exporting within the limit
Screens shown are illustrative — layouts simplified and values fictional.
Scheme at a glance
| Compliance | Fully type-tested to ENA EREC G100 Issue 2 Amendment 2 (G100/2) for export and import limitation · ENA Type Test Register ref. ENICT/19509/V1 — Fully Type Tested, Great Britain |
|---|---|
| Direction | Export limitation, import limitation, or both in one scheme — export held inside the MEL and import inside the MIL from the same point of supply |
| Control modes | Simple trip schemes, or full dynamic control — curtailing generation on export, holding load back on import — matched to the site |
| Format | Standalone wall-mounted panel, or fully integrated into your PVDB, main switchboard or control panel |
| Technologies | Export: solar PV, battery storage (BESS), wind, hydro, diesel generation. Import: controllable loads such as EV charge points, battery charging and heat pumps — confirmed at quotation |
| Measurement | Point-of-supply metering — true net site flow, not a single circuit — three-phase |
| Control interfaces | Modbus RTU/TCP, digital and analogue signals to inverters, generator controllers and battery systems. Control of charger and other load power is engineered to the interfaces your equipment provides — confirmed at quotation |
| Fail-safe behaviour | Fail-safe on loss of measurement, comms or power — generation to a safe state on export, load shed or reduced on import — with a timed trip after repeated or prolonged excursions, per EREC G100 |
| Integration | Combines with G99 protection, PV distribution boards and metering in one assembly |
| Monitoring | Pairs with the Plantstream monitoring platform — IEC 61724-1 Class A-capable solar monitoring |
| Lead times | Standard configurations: short lead times. Bespoke site-specific schemes: typically 5–6 weeks |
| Documentation | Scheme description, settings schedule and Appendix C (Form C) carrying the register reference, for your DNO submission |
The paperwork arrives with the panel
A G100 scheme is only as good as the evidence behind it — export or import. Every ENICO scheme ships with the documents your DNO expects to see, and they stay one QR scan away on the panel for the life of the installation.
- Verifiable listing on the ENA Type Test Register — ref. ENICT/19509/V1
- Scheme description, settings schedule and single-line diagram — export limit or import limit
- Completed Appendix C (Form C) carrying the register reference, ready for your DNO submission
- DNO on-site testing supported where the DNO chooses to attend; settings sealed after acceptance
Planning a constrained connection?
Send us the connection offer and what's on the schedule — inverters, batteries, chargers, heating plant — and we'll tell you whether a G100 scheme fits the constraint, in whichever direction it sits, and price the scheme that does: standard configurations in hours.
Get a G100 quote// Monitoring & verification
See the limit being kept
A limit you can't see is a limit you can't trust. Pair the scheme with the Plantstream monitoring platform and the site shows its workings — export against the agreed limit, curtailment as it happens, and an event log a DNO or client can audit.
- Export, generation and curtailment visible — per site and per inverter group
- Every curtailment logged as an event — an auditable compliance trail
- IEC 61724-1 Class A-capable solar performance monitoring
G100 questions, answered
Do I need G100 export limitation?
If the DNO's connection offer caps your export below what your generation could produce, an export limitation scheme under EREC G100 lets you install the full system and stay within the agreed limit — instead of downsizing the array or battery, or paying for network reinforcement.
What is import limitation and when is it used?
The scheme holds what the site draws from the grid at or below the Maximum Import Limit (MIL) agreed with the DNO. It is used where new controllable load — EV chargers, a battery charging from the grid, heat pumps — could take the site past its agreed import capacity if everything ran at full power at once; the scheme holds that load back as the site approaches the limit. The ENICO G100 Controller is type-tested for import limitation as well as export. Whether a DNO offers limitation or reinforcement at a given site is its decision.
Can the same scheme limit import as well as export?
Yes. G100 Issue 2 assumes a limitation scheme controls both directions unless it is declared export-only or import-only, and one ENICO G100 Controller manages both at the same site — export held inside the MEL and import inside the MIL from the same point of supply. The import limitation page covers the solar + storage + charging case.
What's the difference between G99 and G100?
G99 is about protection — disconnecting your generation when the network needs it to. G100 is about limitation — continuously keeping your export inside the agreed export limit, or your import inside the agreed import limit. A solar or storage site often needs both; where both apply, we build them into one panel with one set of documentation.
What does ENICO's Fully Type Tested controller do for my project?
ENICO's share of the paperwork and testing is done before your panel is built. Fully Type Tested is the register status for a scheme type tested by its manufacturer against EREC G100 Issue 2 Amendment 2, the edition DNOs call G100/2, with every unit declared to be built and to perform the same way; ENICO's G100 Controller holds it on the register for Great Britain. The type tests and declaration your DNO relies on are already lodged there, so your Form C quotes the register reference and Form B is not required. Every panel is built to the tested design.
Will the DNO test it on site, and what does the visit involve?
Whether to witness commissioning is your DNO's decision. For a Fully Type Tested scheme such as ENICO's, site testing reduces to the fail-safe checks: power and communications are cut to each part of the scheme in turn, and each time the controller must go to its safe state and reset once they are restored. The limits are then set and checked. Where your DNO does choose to witness, the visit is booked into its diary and may be chargeable, so allow for the lead time. The panel arrives pre-configured, we support the visit, and the settings are sealed after acceptance.
What is a CLS?
CLS is the abbreviation EREC G100 uses for a Customer Export or Import Limitation Scheme; DNOs such as National Grid Electricity Distribution call it a Customer Limitation Scheme. ENICO's G100 Controller, with its measurement at the point of supply, is the CLS: it controls generation, storage or load to keep the site within its limits. Your connection offer sets those limits as a Maximum Export Limit (MEL), a Maximum Import Limit (MIL), or both. Export limitation holds the MEL; import limitation holds the MIL. One ENICO controller can hold both at the same site.
Can the scheme use a dump load instead of trimming the generation?
Yes, where it suits the site. G100 allows a scheme to control load as well as generation, so a dump load sits within the standard. Where the generator cannot be turned down, the controller diverts surplus into heating, hot water or a thermal store and the generator keeps running in normal operation. Two conditions apply: if the scheme goes to its safe state, it acts on the generation; and if the load cannot absorb the surplus, the scheme still holds the export limit by trimming or tripping the generation. ENICO engineers the load, its rating and its interface to the site, confirmed at quotation.
Standalone panel or built into other switchgear?
Either. We supply the scheme as its own wall-mounted panel, or fully integrated into the switchgear it belongs with — a PV distribution board, a main switchboard or a control panel — sharing metering and protection where that makes the installation cleaner. It can also share an assembly with G99 protection and generation metering. One panel, one delivery, one set of commissioning paperwork.
Which inverters, generators and controllers does it work with?
The scheme controls generation over standard interfaces (Modbus RTU/TCP, digital and analogue signals), so it works with the mainstream solar and battery inverter brands and generator controllers. Control of charger and other load power is engineered to the interfaces your equipment provides. Tell us what's on your schedule and we'll confirm compatibility with the quotation.
Does import limitation work with EV chargers?
EV charge points are one of the loads G100 names explicitly. The scheme measures net import at the point of supply and holds charger power back as the site approaches the Maximum Import Limit. Many chargers offer a power-limit interface; we engineer control to the interface your chargers provide and confirm compatibility at quotation. The import limitation page covers charging hubs in more depth.
Often combined with
Pricing a G100 scheme?
Send the DNO connection offer and your schedule — inverters, generators, chargers or batteries — and we'll quote the scheme that fits, export or import. Standard configurations priced in hours; bespoke site-specific schemes priced properly.