Stoke-on-Trent, UK

G99 vs G100: which do you actually need?

Two Engineering Recommendations, two different jobs — protection and limitation. Here's the plain-English version, and how to tell which applies to your project.

6 min read

If you're connecting generation to the grid in Great Britain — solar, batteries, wind, hydro, CHP or generators running in parallel with the mains — you'll meet two Engineering Recommendations from the Energy Networks Association: G99 and G100. They get mentioned together so often that they blur into one, but they do completely different jobs, and plenty of projects need only one of them.

G99 is about protection

G99 answers the network operator's first question: if something goes wrong, will your generation disconnect when the network needs it to? A G99 protection scheme watches the mains — voltage, frequency, loss of mains — and trips your generation off when conditions leave the limits written into your connection agreement.

Every generator that operates in parallel with the grid needs G99 protection appropriate to its size, from a single rooftop inverter (where it's built into the inverter under G98/G99 type testing) up to multi-megawatt sites with dedicated relay panels, CT/VT metering and witness-tested settings.

G100 is about limitation

G100 answers a different question: how do we stop your site exporting (or importing) more than the connection agreement allows — continuously, automatically, and provably? That's an Export Limitation Scheme: measure true site export at the point of supply and hold export within the agreed limit — a simple scheme trips generation, a dynamic scheme trims it so the site keeps generating.

The same standard — its full title is Technical Requirements for Customers' Export and Import Limitation Schemes — also governs import limitation: holding what a site draws inside its agreed import limit, which is where EV charging hubs, grid-charged batteries and heat pumps come in.

On the export side, you need G100 when the DNO offers you less export capacity than your generation could produce. Without it, the choice is shrink the system or pay for network reinforcement. With it, you can install the array or battery the site needs and cap what leaves the site instead.

The one-line test

Ask two questions about your project:

  • —Will generation run in parallel with the mains? Then G99 protection applies — always.
  • —Is your export capped below what your generation could produce? Then you also need a G100 export limitation scheme. Could new load push you past your agreed import capacity? A G100 import limitation scheme is one of the routes your DNO may offer.

Why a Fully Type Tested scheme matters

For a scheme Fully Type Tested to EREC G100 Issue 2 Amendment 2 (G100/2) and listed on the ENA Type Test Register, the manufacturer's share of the paperwork and testing is done before the panel is built, and commissioning day is a set of safety checks rather than a full demonstration. The ENICO G100 Controller is one such scheme, for export and import; our register entry is shown on the G100 product page.

Most constrained sites need both

A constrained connection usually means one panel doing two jobs: G99 protection to disconnect when the network demands it, and G100 limitation to stay inside the agreed capacity the rest of the time. We build them into a single assembly — shared metering where appropriate, one set of documentation, one commissioning — and for solar work, the same panel can carry the generation metering and monitoring too.

Planning a constrained connection? Send us the connection offer and your generation or load schedule — we'll tell you straight what the scheme needs.

See the G100 export & import scheme